Sunday, April 26, 2026

Garage Lighting, Building 3, 4 ,5, 6, and 8

Our electrical contractor, Critical Peake, will be on-site to install new garage ceiling fixtures.  On Wednesday, April 27, 2026, they will start in Building 4. Building 3 will follow.

Installations will continue throughout the month of May.

Notices will placed in each building a few days before work begins. Automobiles need to be moved outside during the installation.

The new fixtures will be motion sensing. This featrure will save much money on our electric bills.

Learn More




Saturday, April 25, 2026

RoofIng Project Update, April 22, 2026

Roofing Project Update

As of Wednesday April 22, 2026

Katchmark Construction is on site today to continue the scope of work on building #7. Crew is currently 
working on flashing all walls.
~ Starting Thursday, we will go back to building #5 to start installing metal counter flashing and re-secure lightning cable rods back down to the roof decking.

Monday, April 20, 2026

Roofing Projects Update April 17, 2026

Katchmark Construction is on site to continue the scope of work on building #7 and are 40% completed with building #7.

So Far buildings #5,#4, and #9 are 99% completed, Katchmark will work on installing metal counter flashings on these buildings this week.

Katchmark Report with pictures


Friday, April 17, 2026

April Electric Billing Report

These tables and chart compares Year-over-Year electric bills for 2025 and 2026.

Bottom line: the cumulative billed cost reduction was $7995.98.

 Click here for a printable version of the report.








Saturday, April 11, 2026

Building 5 restoration

Building 5 Restoration begins on Monday, April 13, 2026.

Parking near building 5 will be restricted to permit staging of materials and construction vehicles.

Click here for Parking Plan

First floor deck removal. Residents will have acccess to walkways.






Thursday, April 9, 2026

Garage Lighting Project Update April 9, 2026

Critical Peake, the electrical contractor, has secured a grant from Delaware Department of Natural Resources and Enviormental Control. The next step is to secure a grant from Delaware Electric Co-operative.

Critical Peake has installed two light fixtures In Building 5's garage for testing.  The lights are motion sensing. The requirement is that the lights sense people and vehicles as they pass below. The lights will remain illuminated for 10 minutes after motion has ceased. 

The association wants to be sure that the lights work properly before installing 270 lamps. You will find these LED lights brighter and cleaner. They will not rust and they are vapor proof and therefore bug-proof.

The fixtures are 40 watts replacing 80 watt flouresecent fixtures. The main savings will be derived by the motion sensing feature. 

As soon as Delaware Electric Coop delivers their grant, installation in all garages will begin.  

Stay Tuned.










Wednesday, April 1, 2026

Roofing Project begins in Windswept

 Roofing materials delivered this morning.

The materials will be lifted to the roof and work will begin.

Your condo assessment at work.

Buildings 4,5,7, and 9 are scheduled for 2026. 

Starting with 5, 4, 9, 7.

Bldg. 5 is 99% complete (need to install metal flashing)

Bldg. 4 - finishing 4/13

Bldg. 9 - starting Tuesday 4/14 or Wednesday 4/15

Bldg. 7 - starting Friday 4/17 or Monday 4/20

 

Under layment board installed

TPO water proof roofing installation