Roofing materials delivered this morning.
The materials will be lifted to the roof and work will
begin.
Your condo assessment at work.
Buildings 4,5,7, and 9 are scheduled for 2026.
Starting with 5, 4, 9, 7.
Bldg. 5 is 99% complete (need to install metal flashing)
Bldg. 4 - finishing 4/13
Bldg. 9 - starting Tuesday 4/14 or Wednesday 4/15
Bldg. 7 - starting Friday 4/17 or Monday 4/20
![]() |
| Under layment board installed |
![]() |
| TPO water proof roofing installation |